Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
CH Demand
CH Selector in Maximum position
ON/OFF Switch in ON position
Summer/Winter in Winter Position (IN)
Timer Set to ON Position
CH Selector in Maximum position
ON/OFF Switch in ON position
Summer/Winter in Winter Position (IN)
Timer Set to ON Position
Gain access to clock connections (use insulation mat as necessary)
| WARNING! Mains voltage is expected during test, follow TOPs P4 live testing procedure |
Measurement:
On the back of the Timer measure the voltage between the two orange wires connected to terminals 3 and 5.
With the Timer set to ON expect 0v DC across the connection
Note:
If external controls are not fitted ensure the link is in place.
With the Timer set to ON expect 0v DC across the connection
Note:
If external controls are not fitted ensure the link is in place.

Isolate as per TOPs P4
and refit as necessary