Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to DC Volts Set meter to measure DC Volts
Remove 4 wire cable from fan assembly
Ensure NO demands
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Measure the DC voltage between the red wire at X4 on the PCB and a suitable earth.
Expect approximately 40 Vdc.
Notes:
1. Fan may be running during test due to signal control connector being disconnected.
2. Boiler may enter lockout during test, reset boiler as required until test complete
3. Test at PCB connector can be carried out on either the small holes or the larger silver soldered points.
4. There is no need to wait for the purge cycle to complete or to reset lockout before carrying out this test.