Set Appliance State:
Mains Power Off
Locate system filing loop
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Test 1:
Measure for DC voltage between pin 14 (Green) on X25 and the
earth point on the boiler chassis - make a note of the voltage measured.
Test 2:
Slightly Increase the system pressure and repeat Test 1.
Has the voltage increased after the increase in system pressure ?
Note:
Each pin on the PCB connector is numbered.
Measure for DC voltage between pin 14 (Green) on X25 and the
earth point on the boiler chassis - make a note of the voltage measured.
Test 2:
Slightly Increase the system pressure and repeat Test 1.
Has the voltage increased after the increase in system pressure ?
Note:
Each pin on the PCB connector is numbered.