Set Appliance State:
Gas Off
| Isolate Mains Power to appliance as per TOPs P4 |
CH Demand
Attach a pressure gauge to the inlet pressure test point
(there may also be a test point on the isolation valve - use whatever is easier)
(there may also be a test point on the isolation valve - use whatever is easier)
Gas On
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Observation:
Allow boiler to begin ignition sequence.
Does the inlet pressure remain satisfactory throughout?
Notes:
1. When pressure gauge is removed the pressure test point should
be tightened and checked for gas tightness.
2. Refer to TOPs for more information on acceptable inlet pressures.
Does the inlet pressure remain satisfactory throughout?
Notes:
1. When pressure gauge is removed the pressure test point should
be tightened and checked for gas tightness.
2. Refer to TOPs for more information on acceptable inlet pressures.
Isolate as per TOPs P4
and refit as necessary