Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
CH Demand
Gain access to PCB (use Insulation Mat as required)
Thermostat to Max position
Thermostat to Max position
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Test 1:
Measure Mains Voltage across the pump Live terminal (marked L) and the pump Earth terminal on the pump connector block.
Test 2:
Measure Mains Voltage across the pump Neutral (terminal (marked N) and the pump Earth terminal (Blue) on the pump connector block.
Measure Mains Voltage across the pump Live terminal (marked L) and the pump Earth terminal on the pump connector block.
Test 2:
Measure Mains Voltage across the pump Neutral (terminal (marked N) and the pump Earth terminal (Blue) on the pump connector block.