Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
Turn Hot Water Tap On
Gain access to PCB (use Insulation Mat as required)
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
If required, reset boiler, press mode and ok for 2 seconds.
Allow self-check to complete and ignition sequence to commence.
Measure for A/C voltage across the brown and blue wires of connector 54.
Expected voltage, mains voltage (see note 3.).
Allow self-check to complete and ignition sequence to commence.
Measure for A/C voltage across the brown and blue wires of connector 54.
Expected voltage, mains voltage (see note 3.).

Isolate as per TOPs P4
and refit as necessary