Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
Turn Hot Water Tap On
Gain access to PCB (use Insulation Mat as required)
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Allow boiler to ignite and establish.
Measure the voltage between pins 1 (grey)
and 2 (black) at connector J7 on the control PCB.
Voltage should be approximately 9V DC or greater.
Measure the voltage between pins 1 (grey)
and 2 (black) at connector J7 on the control PCB.
Voltage should be approximately 9V DC or greater.

Isolate as per TOPs P4
and refit as necessary