Set Appliance State:

Gas Off
Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Turn Hot Water Tap On
Gain access to PCB (use Insulation Mat as required)
DHW temperature selector to maximum
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Allow fan to run and ignition sequence to commence.
After approximately five seconds:
Test 1: Measure the voltage between connection 4 (Blue wire) and connection 3 (Brown wire) of PCB connector A1.
Test 2: Measure the voltage between connection 4 (Blue wire) and connection 2 (Black wire) of PCB connector A1.
Voltage will only be present for approximately 10 seconds.
As burner will not ignite, boiler may go to lockout.
Reset appliance and retest as necessary.