Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Turn Hot Water Tap On
Remove connector from spark generator and make safe
Selector switch to DHW position
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Reset as required. Allow fan to run and ignition sequence to commence.
Approximately 5 seconds after the fan starts measure the voltage between connections 26 (brown wire) and 25 (blue wire) at M4 on the PCB.
Mains voltage should be present.
Note:
Voltage drop will only be present for approximately 10 seconds,
boiler may go to lockout. Reset appliance and retest as necessary.