Set Appliance State:

Gas Off
Isolate Mains Power to appliance as per TOPs P4
Turn Hot Water Tap On
Attach U-gauge to inlet pressure test point
(To open Honeywell valve test point use tool provided
if available, if needed use T10 torx / 2mm Allen key)
Gas On
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Observation:

Reset appliance as necessary and allow the boiler to complete its self-check.
Monitor the pressure gauge as the appliance operates, the pressure should remain above the minimum quoted in the table.
Does the inlet pressure remain satisfactory?
Note:
Upon completing of the test the test point should be tightened and checked for gas soundness.