Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
Gain access to PCB (use Insulation Mat as required)
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Allow fan fault code to occur.
Measure the voltage between the brown wire marked 13.4 and the blue wire marked 13.5 within 2 minutes of the appliance entering fan lockout.
Mains voltage should be present.
Note:
After 2 minutes the voltage to fan assembly will no longer be present, if required reset the appliance and allow it to re-enter fan lockout to confirm the outcome of the test.
Measure the voltage between the brown wire marked 13.4 and the blue wire marked 13.5 within 2 minutes of the appliance entering fan lockout.
Mains voltage should be present.
Note:
After 2 minutes the voltage to fan assembly will no longer be present, if required reset the appliance and allow it to re-enter fan lockout to confirm the outcome of the test.

Isolate as per TOPs P4
and refit as necessary