Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Disconnect electrical connector from the fan
assembly, position in a safe place
Ensure NO demand
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Click here for more information before carrying out this test.
Reset appliance press and hold reset button for 5 seconds, then release.
Preheat OFF (ECO button illuminated), this should be done A.S.A.P after reset has completed
to prevent the boiler attempting to run the fan. (pump should not be running if it is repeat the above)
Test 1:
Measure for AC Voltage across terminals 2 (Brown) and 4 (Yellow) of connector ST5 and
note the reading.
Test 2:
Turn Hot Water Tap On, DHW Temperature Control to MAX.
Measure for AC Voltage across terminals 2 (Brown) and 4 (Yellow) of connector ST5 again.
Expect an increase in voltage of approximately 1.3 VAC or greater from the original voltage
measured on the first test.
NOTE: If appliance lockout occurs (approx after 30 seconds) during test, reset appliance as required until test complete.