Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
Turn Hot Water Tap On
Gain access to PCB (use Insulation Mat as required)
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Cancel purge cycle & If required, reset boiler.
Measure for A/C voltage across pins 1 & 4 of connector CN2.
Expect mains voltage.
Note:
Connector CN2 may differ in appearance but test points remain the same.
Measure for A/C voltage across pins 1 & 4 of connector CN2.
Expect mains voltage.
Note:
Connector CN2 may differ in appearance but test points remain the same.

Isolate as per TOPs P4
and refit as necessary