Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Turn Hot Water Tap On
Gain access to PCB (use Insulation Mat as required)
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Cancel purge cycle & If required, reset boiler.
Measure for voltage between pins 6 and 5 at connector CN2 on the PCB.
During the sparking stage of the ignition sequence (5 - 10 seconds
after purge cycle is cancelled) mains voltage should be present.
Note:
Boiler may enter lockout during test,
reset and repeat test as necessary.