Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
CH Demand
Gain access to PCB (use Insulation Mat as required)
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Cancel purge cycle & If required, reset boiler.
Allow the boiler to operate for CH.
Measure the A/C voltage across the outer pins
(brown and blue) of connector CN4.
Mains voltage should be present.