Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Gain access to PCB (use Insulation Mat as required)
Selector switch set to CH/DHW
CH temperature control set to MAX
Preheat switched OFF
Note.
Slightly move connectors until PCB connection strips
are exposed for voltage measurement
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Step 1. Run a hot tap (DHW demand) for approx. 10 seconds then close tap.
Step 2. Place a CH demand on appliance.
Measure for AC voltage across pin 3 (X2 connector PCB) and
main neutral (terminal block).
Expected voltage approximately 230 Vac
Note. It may take several attempts to confirm voltage, as it is only present for approx. 5 seconds, repeat steps 1 & 2 until test is complete.