Set Appliance State:
Mains Power Off
Selector switch set to CH/DHW
Preheat switched OFF
CH temperature control set to MAX
DHW temperature control set to MAX
Preheat switched OFF
CH temperature control set to MAX
DHW temperature control set to MAX
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Observation:
Test 1.
Apply a CH demand and allow boiler to run for 2 minutes, then remove CH demand.
Fan and pump should both run for approximately 4 minutes.
Test 2.
Apply a DHW demand and allow boiler to run for 2 minutes, then remove DHW demand.
Fan should run for approximately 4 minutes and the pump
for approximately 60 seconds.
Apply a CH demand and allow boiler to run for 2 minutes, then remove CH demand.
Fan and pump should both run for approximately 4 minutes.
Test 2.
Apply a DHW demand and allow boiler to run for 2 minutes, then remove DHW demand.
Fan should run for approximately 4 minutes and the pump
for approximately 60 seconds.
Isolate as per TOPs P4
and refit as necessary