Set Appliance State:
Mains Power Off
CH Demand
Selector switch set to CH/DHW position
Boiler CH thermostat set to MAX
Ensure CH controls are calling for heat
Boiler CH thermostat set to MAX
Ensure CH controls are calling for heat
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Observation:
Allow the burner to ignite and run with a CH demand for approx. 30 seconds.
Remove the CH demand.
Does the pump continue to run for approximately 10 seconds ?
Remove the CH demand.
Does the pump continue to run for approximately 10 seconds ?
Isolate as per TOPs P4
and refit as necessary