Set Appliance State:

Gas Off
Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Turn Hot Water Tap On
Selector switch set to ch/dhw
Dhw temperature control set to max
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Allow ignition sequence to start.
After approximately 5 seconds measure for mains voltage across connections 1 (blue) and 2 (brown) on connector CN5 on the PCB.
Expect mains voltage.
Voltage will only be present for approximately 5 seconds during the ignition phase, the appliance will try to ignite once before going to lockout.
Note:
Reset boiler as required to complete test.