Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Turn Hot Water Tap On
Set selector switch to ch/dhw
Dhw temperature control to max
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Allow ignition sequence to commence.
Measure for AC voltage across connection blue (neutral) connector CN1 (black probe)
and at connections blue and brown on connector CN6.
Test 1. Blue connection CN6, expected voltage varies between 185 - 230 vac.
Test 2. Brown connection CN6, expected voltage varies between 185 - 230 vac.
Note:
Voltage will only be present during the sparking stage of the ignition sequence,
this will last for approximately 5 seconds, the appliance will then go to lockout.
Reset boiler as required until test complete.