Set Appliance State:

Mains Power Off
CH Demand
Selector switch to DHW and CH position
CH temperature selector to maximum
DHW temperature selector to minimum
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Observation:

Allow burner to ignite and establish and the boiler to run on central heating until the radiators begin to warm.
Remove heating demand i.e. turn clock to off period.
Does pump continue to run for between 1 and 3 minutes?
Note:
The actual time of the overrun will depend on the temperature of the boiler when turned off but should not be longer than 3 minutes.