Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to DC Volts Set meter to measure DC Volts
Gain access to PCB (use Insulation Mat as required)
DHW temperature selector to Max
WARNING! Mains voltage is expected during test, follow TOPs P4 live testing procedure
Mains Power On

Measurement:

Measure the voltage between the grey wires on connector X4 at the PCB.
Shortly after the pump begins to run the voltage
should drop from 26V to approximately 0V DC.
Continue to monitor the voltage until the boiler cuts out.
Does the voltage change back to 26VDC indicating the
flow switch has cut out or does the voltage remain at 0V?