Set Appliance State:
Mains Power Off
Turn Hot Water Tap On
Gas On
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Allow fan to run and ignition sequence to commence.
Test 1: Measure the voltage across blue and red wires at the gas valve.
Expect approximately 120 volts AC or greater.
Test 2: Measure the voltage across black and white wires at the gas valve.
Expect approximately 26 volts AC or greater.
Note:
If burner does not ignite voltage will only be present for approximately 8 seconds
during sparking phase then appliance will go to lockout reset as necessary.
Test 1: Measure the voltage across blue and red wires at the gas valve.
Expect approximately 120 volts AC or greater.
Test 2: Measure the voltage across black and white wires at the gas valve.
Expect approximately 26 volts AC or greater.
Note:
If burner does not ignite voltage will only be present for approximately 8 seconds
during sparking phase then appliance will go to lockout reset as necessary.

Isolate as per TOPs P4
and refit as necessary