Set Appliance State:

Mains Power Off
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Observation:

Test 1.
Apply a DHW demand and allow boiler to ignite and run for 30 seconds, then remove DHW demand.
Pump overrun should run for approximately 30 seconds.
Test 2.
Apply a CH demand and allow boiler to ignite and run for 30 seconds, then remove CH demand.
Pump should overrun for approximately 5 minutes (factory set).
Does the pump overrun operate as expected?
Note:
Early versions of these appliances had a pump without PWM control even though a wire for it is present (these pumps can be identified by not having the letter "IZA" after the pump model number) for these pumps DHW overrun will be 2.5 minutes and CH overrun will be 7 minutes.