Set Appliance State:
Ensure No demands are present
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Reset boiler as required.
Allow the boiler to commence self check mode.
Measure for A/C voltage across the condensate pump terminals.
Expected voltage mains voltage (see note).
Note.
Voltage may only be present for approximately 20 seconds after boiler is reset, repeat test from set state as required,
Allow the boiler to commence self check mode.
Measure for A/C voltage across the condensate pump terminals.
Expected voltage mains voltage (see note).
Note.
Voltage may only be present for approximately 20 seconds after boiler is reset, repeat test from set state as required,

Isolate as per TOPs P4
and refit as necessary