Set Appliance State:
| Isolate Mains Power to appliance as per TOPs P4 |
CH Demand
Gain access to PCB (use insulation mat as required)
Pull connector X3 back slightly to expose test points
Pull connector X3 back slightly to expose test points
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Reset appliance as necessary.
Measure the voltage between pin 4 (brown) and pin 5 (blue) at X3 on the PCB.
At 15 second intervals mains voltage should be measured
for 3 seconds as power is sent to the spark generator, this
will be repeated 5 times until lockout occurs.
Is the voltage measured as expected?
Notes:
1. Timings quoted are approximate.
2. Reset appliance and repeat test as necessary until outcome is determined.
Measure the voltage between pin 4 (brown) and pin 5 (blue) at X3 on the PCB.
At 15 second intervals mains voltage should be measured
for 3 seconds as power is sent to the spark generator, this
will be repeated 5 times until lockout occurs.
Is the voltage measured as expected?
Notes:
1. Timings quoted are approximate.
2. Reset appliance and repeat test as necessary until outcome is determined.

Isolate as per TOPs P4
and refit as necessary