Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to Resistance Set meter to measure resistance
Disconnect wires from APS
Remove APS from boiler
Attach crocodile clips to exposed spades on the APS

Measurement:

Note the operating pressure indicated
on the pressure switch.
Connect the air pressure switch charge kit to
P1 on the air pressure switch.
Ensure the performance tester reads 0mb.
Short circuit (zero resistance) should be measured.
Slowly increase the pressure via the syringe.
Short circuit should continue to be measured until the pressure is equal to that indicated on the pressure switch, at which point the resistance should change to open circuit.
Notes:
100Pa (Pascals) = 1millibar