Set Appliance State:
Mains Power Off
CH Demand
Gain access to PCB (use Insulation Mat as required)
Ensure that the Boiler Thermostat is set to MAX
Ensure that the Boiler Thermostat is set to MAX
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Allow the fan to run for approximately 10 seconds and measure the voltage across the black spaded wire and blue wires at the molex plug running between the PCB and the gas valve.

Isolate as per TOPs P4
and refit as necessary