Set Appliance State:

Gas Off
Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to AC Volts Set meter to measure AC Volts
Gain access to PCB (use Insulation Mat as required)
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Allow boiler self check to complete.
Hold down the service mode button for more than 5 seconds to enable service mode.
Measure the voltage across L and N on the green mains
connector (middle plug) for the pump.
Mains voltage expected.
Once test is completed press the service mode
button once to turn service mode off.