Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4

Measurement:

WORCESTER GREENSTAR RI
CASE REMOVAL
1. Undo and remove 2 screws (A) securing
the boiler casing at the top of the appliance.
2. Undo but do not remove the 2 screws (B) securing
the boiler casing at the bottom of the appliance.
3. Pull case forward and remove.