Set Appliance State:
Mains Power Off
CH Demand
On/Off Switch On.
Gas On
| WARNING! Mains voltage is expected during test, follow TOPs P4 live testing procedure |
Measurement:
Allow approximately 20 seconds after the Boiler is switched on for the PCB to sequence the combustion purge period and measure Mains Voltage across the White wire (connection 14) and the Blue wire (connection 7) on the PCB connector.

Isolate as per TOPs P4
and refit as necessary