Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to DC Volts Set meter to measure DC Volts
CH Demand
Selector Switch to Hot Water and Heating
Gain access to PCB (use insulation mat as necessary)
Remove connector from spark generator and make safe
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Allow fan to run.
Using shrouded probes measure voltage across the outer brown and blue terminals on the PCB at X2 on the front of the lowered control box.
Exact voltage will vary but it should be at least 100V DC.
Make a note of the voltage recorded as it will be needed on the next test.
Note:
Voltage will only be present approx. 8-10 seconds after mains power is turned on.
The voltage will only be present for around 4 seconds.
Reset boiler and repeat test as necessary