Set Appliance State:
Mains Power Off
CH Demand
On-Off switch on
| WARNING! - Mains voltage is expected during test follow TOPs P4 live testing procedure |
Measurement:
Allow the ignition sequence to commence fan running.
Measure the DC volts at the fan connector between each wire listed in the table below.
Connection to the fan leads can be made by inserting the probe in the hole on the fan connector.
Voltages should be approx. as follows;
Measure the DC volts at the fan connector between each wire listed in the table below.
Connection to the fan leads can be made by inserting the probe in the hole on the fan connector.
Voltages should be approx. as follows;

Isolate as per TOPs P4
and refit as necessary