Set Appliance State:

Isolate Mains Power to appliance as per TOPs P4
Set Multimeter to DC Volts Set meter to measure DC Volts
CH Demand
Gain access to PCB (use insulation mat as necessary)
Mains reset switch On
WARNING! - Mains voltage is expected during test follow
TOPs P4 live testing procedure
Mains Power On

Measurement:

Insert the probes behind the wires at the back of the connector and ensure good connection.
After approximately 6 seconds measure voltage across connection 1 (brown lead) and connection 4 (blue wire) on connector H2 on the main PCB (this is ignition attempt one).
Expected voltage greater than 70 volts DC
There will be three ignition attempts, the second 7 seconds after the first and the third 30 seconds after the second.
Note: The voltage will be greater than 70 volts DC for approximately 3 seconds while power is thrown to the spark generator. Expected voltages outside the ignition attempts to be 20-50 volts DC.